Solar remove and reinstall for a reroof: permits, plans and the attachment sequence

10 min read · Verified

Short answer

Taking a solar array off for a reroof and putting it back is called a remove and reinstall (R&R, or detach and reset). Many building departments treat it as two permits: a reroof permit for the roofer, and an electrical or solar permit for removing and reinstalling the array, usually held by a licensed electrical or solar contractor. Some want a plan set showing the attachments on the new roof; a few treat the reinstall as a brand-new system that must meet current code. The most common field mistake is the order of work: on shingle roofs the new shingles go on first and the flashed attachment goes in after, tucked under the course above.

What a remove and reinstall involves

When a roof under an existing solar array needs replacing, the array has to come off first. The modules, rails and attachments are removed and stored, the roof is replaced, new attachments go in, and the same system goes back up and is reconnected. Roofing contractors handle a large share of these jobs, because the reroof is what drives them, and the homeowner expects one company to manage it.

It looks simple: same panels, same inverter, same layout. In practice it touches the roof, the structure and the electrical system, and building departments review it that way.

Does a remove and reinstall need a permit?

In most places, yes, and often two:

  • A reroof permit for the roofing work.
  • An electrical or solar permit for disconnecting, removing and reinstalling the array.

How departments handle the details varies widely. These are the patterns we see across their published handouts:

What departments ask forHow it shows up
A licensed contractor for the solar workSeveral California cities state that a roofing-only contractor or the homeowner may not remove and reinstall the PV system; the solar permit goes to an electrical, solar or general contractor
Plans for the reinstallRequired by some departments for every R&R, by others only when the layout, attachments or equipment change
A new permit when anything changesMoving modules, adding modules or changing equipment is treated as new solar work with its own plan review
Signed formsAffidavits from both the roofer and the solar contractor, or a homeowner acknowledgment, before the reroof permit is issued
Inspection orderSome won’t final the reroof until the array is back on and the solar permit has passed inspection
Treated as new workA few treat any reinstall as a brand-new system, with current-code engineering, plan review and inspection

The one question to ask the building department in writing before you bid: is a reinstall of an existing, permitted system reviewed as existing work, or as new work under the current code? The answer decides whether old equipment can go back as it was.

The current-code question: rapid shutdown and old equipment

Systems installed before rapid shutdown was required often have string inverters with no module-level shutdown. If the department treats the reinstall as new work, that system may need rapid-shutdown equipment added before it can go back up, which changes the scope and the price of the job. Some departments let a previously permitted system return as it was; others don’t. Find out before the bid, not after the tear-off.

The same applies to fire setbacks. An array that was installed before the current pathway rules may not fit on the roof the same way if the reinstall is reviewed as new. See fire access pathways and setbacks and rapid shutdown labeling.

What an R&R plan set shows

Where plans are required, a remove-and-reinstall set is shorter than a new-system set, but it covers the parts that change with the roof:

  • Scope of work stating that the existing system is removed and reinstalled with no change in equipment or capacity, or listing exactly what changes.
  • Site and roof plan with the array as it will be reinstalled, the roof area and slope, and fire setbacks where the department applies them.
  • Attachment layout on the new roof: rafter or truss locations, attachment spacing and the rail layout.
  • Attachment detail for the new roof covering. If the roof changes from shingle to tile or metal, the attachments change too, and so does the detail.
  • Structural check where the new roof is heavier, the attachment spacing increases, or the department’s no-calculation limits are exceeded. See when you need a structural stamp.
  • Single-line diagram of the existing system, with labels and placards.
  • Specification sheets for the racking and the flashing products used on the new roof.

The order of work: roofing first or attachment first?

This is where we see the most mistakes on reroof jobs. The roofing crew and the solar crew each know their own trade, and the attachment sits right where the two meet. The order depends on the roof covering and on the attachment product, so the attachment detail on the plans and the manufacturer’s installation instructions always come first. The usual sequence:

Roof coveringUsual attachmentOrder of work
Composition shingleFlashed L-footNew shingles go on first. Then the flashing slides under the shingle course above the attachment point, and the L-foot and lag go through the flashing into the rafter.
Flat or low slope: rolled composition, or a silicone or other fluid-applied membraneStandoffStandoffs go on first, anchored through the roof deck into the structure at the locations on the plans. Then the rolled roofing or membrane goes on around them, and sealant covers each base so the roofing and standoff form one smooth, sealed surface.
Concrete or clay tileTile hook or tile replacement mountUnderlayment goes on first. Hooks are fastened through their flashing into the rafters as the tiles are laid, and the tiles over the hook arms are notched so they lie flat without the hook bearing on them.
Standing seam metalSeam clampThe metal roof goes on first. Clamps go on the seams afterward, with no penetrations.
Corrugated or ribbed metal (exposed fasteners)Bracket made for the panel profile, such as the S-5! ProteaBracket for trapezoidal ribsThe panels go on first. Brackets are fastened through the panel into the structure with their sealing washers or gaskets.

On flat and low-slope roofs, standoffs-first is the method we recommend, and it’s common on new construction: the standoffs are anchored to the deck, and the roofing covers their bases so there are no separate flashings to fail. That applies to a reroof, where the roofing is going on new. On an existing flat roof that isn’t being replaced, installers do the opposite: the standoff mounts on top of the roofing that’s already there, and a flashing is sealed over its base (see solar roof attachment types). It’s also the clearest reason to have the plans before the roofers start. The attachment layout tells the crew exactly where to anchor each standoff, into which rafter or joist, before the roofing goes down.

Two rules apply on every roof type. Old flashings and seals don’t get reused; use new flashing on the new roof. And every attachment has to land in a rafter or truss: a reroof is the moment to confirm their locations, since a lag that only bites into the sheathing has almost no pull-out strength. The details for each roof type are in solar roof attachment types.

The electrical side

Disconnecting and reconnecting the system is electrical work, done by the licensed contractor named on the solar permit:

  • Before removal: photograph and label every string and connection, shut the system down through its rapid shutdown and disconnects, and confirm it’s de-energized before anyone unplugs a module.
  • Storage: modules stored flat and protected, connectors capped and kept dry.
  • Reinstall: the same strings reconnected as they were, connectors inspected, the system tested and its monitoring confirmed before the final inspection.
  • Warranties: check whether the module and inverter warranties, or the original installer’s workmanship warranty, require an approved installer for removal.

Mistakes we see on reroof jobs

  1. The attachments installed in the wrong order with the roofing, so water runs into the penetration instead of over the flashing.
  2. No solar permit on the assumption that putting the same system back doesn’t need one.
  3. The layout changed on the roof without updated plans: modules moved to fit new vents or a new roof shape.
  4. Attachments that miss the rafters after the deck is replaced and the old holes no longer line up.
  5. The electrical work done by a contractor not licensed for it where the department requires an electrical or solar contractor.

A checklist for roofing contractors

  • Ask the building department, in writing, whether the reinstall is existing or new work.
  • Line up the licensed electrical or solar contractor before the bid.
  • Photograph the array, the strings and the equipment before anything comes off.
  • Get the reroof and solar permits, and the plan set where one is required.
  • On flat and low-slope roofs, anchor the standoffs from the plans before the roofing goes on.
  • Install the attachments in the right order for the roof covering, with new flashing.
  • Schedule the solar inspection before the reroof final where the department links them.

Sources

Checked November 2026 against published reroof-with-solar policies and handouts from city and county building departments, including Santa Cruz County, Thousand Oaks, Foster City, Capitola, Mountain House and Wheaton, Illinois. Requirements differ between departments; confirm yours before you bid.

Roofing contractors: we draw remove-and-reinstall plan sets nationwide, with the attachment layout and details for the new roof, and we offer contractor pricing for roofing companies that send us their reroof jobs. Call 323.682.2282, email info@solardesignsusa.com, or send us a remove-and-reinstall job.